Guide

Utility Interconnection for New Construction Solar

The utility runs on its own calendar. The application is the only lever, and it belongs in construction documents.

Key takeaways

  • Investor-owned utilities (SCE, PG&E, SDG&E) interconnect under Rule 21, with new systems served under the net billing tariff; municipal utilities such as LADWP run their own processes and programs.
  • The interconnection application should be filed during construction documents so utility review runs parallel to construction.
  • Service size, transformer capacity, and export limits can trigger studies or upgrades that take months; discovering them during construction is the risk.
  • Metering, disconnect, and equipment requirements from the utility must be reflected in the permit drawings.

Every solar system on a new building connects to a utility service that is itself new. That creates an opportunity and a trap. The opportunity is that the solar interconnection can be designed into the service from the start. The trap is that the utility's review of both the new service and the solar system runs on the utility's schedule, and nothing on the construction schedule can speed it up.

Investor-owned utilities

Southern California Edison, Pacific Gas and Electric, and San Diego Gas & Electric interconnect customer generation under Electric Rule 21, with export compensation for new systems governed by the CPUC's net billing tariff. The process includes an application, technical review, potential supplemental studies where the system or service raises screens, an interconnection agreement, inspection or witness testing, and permission to operate. Larger systems and systems on larger services are more likely to require studies, and studies take time.

One consequence worth knowing: under AB 2143, nonresidential solar projects served under investor-owned-utility net energy metering or net billing tariffs are treated as public works for prevailing wage purposes, with exemptions for single-family homes, residential systems of 15 kW or less, and multiunit housing of two stories or fewer. The tariff choice has labor cost implications that belong in the budget early.

Municipal utilities

The Los Angeles Department of Water and Power, Anaheim Public Utilities, Riverside Public Utilities, the Sacramento Municipal Utility District, Silicon Valley Power, and other municipal utilities run their own interconnection processes, metering requirements, and solar programs. LADWP, in particular, operates its own net metering program and a Feed-in Tariff that purchases output from larger systems under long-term contracts. The rules of the serving utility shape the design, so the first question on any site is who serves it.

Export, non-export, and sizing

A system can be designed to export surplus production to the grid, to limit export, or to avoid it entirely. The choice affects compensation, the utility's technical screens, and the equipment required. On a new building, where the Energy Code sets a minimum size and the roof may allow much more, the export strategy and the tariff determine whether building beyond the minimum makes sense.

What can go wrong

  • The new service is sized without the solar system and the interconnection exceeds what the service or transformer can accept, triggering an upgrade.
  • The application is filed after construction starts and the utility's review finishes after the building opens.
  • Utility metering and disconnect requirements are not in the permit drawings, and the electrical room has no place for them.
  • The witness test or inspection cannot be scheduled because the system is not complete when the utility is available.

How to keep the utility off the critical path

Identify the serving utility and its programs at concept. Coordinate the new service and the solar interconnection in the electrical design. File the interconnection application during construction documents. Reflect metering and disconnect requirements in the permit set. Track the utility's review alongside the construction schedule and sequence the witness test with the system's completion. We do all of this as part of our scope so permission to operate lands with the Certificate of Occupancy rather than after it.

Questions

When should the interconnection application be filed for a new building?

During construction documents, once the electrical design and system size are fixed. Filing then lets utility review run parallel to construction. Filing after construction starts risks finishing after the building opens.

Does LADWP follow the same rules as SCE?

No. LADWP is a municipal utility with its own interconnection process, net metering program, and Feed-in Tariff. The CPUC's net billing tariff and Rule 21 apply to investor-owned utilities such as SCE, PG&E, and SDG&E.

Can the utility require upgrades for a new building's solar system?

Yes. If the system or the new service raises technical screens, the utility may require studies or infrastructure upgrades. Coordinating the service size and the solar interconnection together in design reduces that risk.

Keep Reading

Related guides.

Solar and the Certificate of Occupancy

The building's final inspection depends on the Energy Code scope being complete and documented. If solar is the last trade on site, solar is the delay.